Your feedback drives the Concourse roadmap! Review and vote for existing ideas or submit new ideas.


For immediate technical support, please follow this guidance to open a Service Now ticket.


1 Not supported for the current status
Status Not started
Feedback Type United States
Created by Manabu Sakamoto
Created on Oct 6, 2023
Merged idea
This idea has been merged into another idea. To comment or vote on this idea, please visit CONC-I-1108 Add Planned Start/Due date for deliverable/task/subtask.

Enhancement Request (Actual Dates) Merged

On the tab of "Concourse Deliverable Management", tasks have 2 attributes for planned date (Start Date & Due Date). Please add 2 more attributes for "Actual Start Date" & "Actual Complete Date".

<Background >

1. To estimate the task duration accurately, we need statistics data by collecting the information of planned & actual dates.

2. To report the status of delayed tasks to the client and managements, Project Managers require to trace them on the Dashboard.

e.g. How many days delayed and how many days the subsequent tasks are expected to delay next week ?

3. Jira can solve this issue, but it is very difficult for our engagements to cash out additional cost for Jira.


Workspace Territory United States
  • Admin
    Courtney Powers
    Oct 9, 2023

    Thank you for this idea! This was similar to an idea that was already in this portal (#1108) so we've merged the two together! Don't worry your vote and comments were transferred over. Thanks again!